Highland Bridge update: Ryan Companies reports progress; gateway building, retail and civic square advancing
Summary
Developers Ryan Companies and Leidner/Widener Apartment Homes updated the HRA on construction progress at Highland Bridge, including a 97-unit gateway building under construction, planned daycare tenant fit-out, reuse of historic Ford plant elements in facades, and timelines for Blocks 11 and 16.
Ryan Companies and a partner developer updated the St. Paul HRA on construction and design progress at the Highland Bridge site, including the gateway mixed-use building, three retail shells along Ford Parkway, the civic square (Outlot B), and early plans for Blocks 11 and 16.
Sean Ryan, a developer with Ryan Companies, told the HRA that construction on the Gateway project (formerly Block 2B/2C and Outlot B) began in June and that the project remains on track for a forecasted turnover date of Oct. 26. He described the Gateway building as a 97-unit market-rate multifamily building with about 23,000 square feet of retail. Ryan reported that footings and foundations are complete, precast structured parking and the parking slab on grade are finished, exterior…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat