Village staff outlines 2025 capital plan; recommends resurfacing Roscoe Center, Hodges Run; Main Street reconstruction estimated at $1.69 million
Summary
Staff presented a draft capital plan and recommended the residential streets program target the Roscoe Center and Hodges Run subdivisions with an estimated $577,182 for full pavement replacement; Main Street reconstruction phase was estimated at $1,692,000 with a proposed additional design fee of $45,900.
At the Dec. 17, 2024 committee meeting, village staff presented a draft 2025 capital program and recommended prioritizing the residential streets program, naming Roscoe Center and Hodges Run subdivisions as the next resurfacing projects. Staff said the two subdivisions have among the lowest pavement-condition ratings in the village and recommended full pavement replacement rather than mill-and-overlay because the existing asphalt thickness and condition do not meet structural overlay requirements.
Brandon (village staff) told trustees the estimated cost to remove and replace pavement in the two subdivisions—bringing paved sections to a 3-inch asphalt depth consistent with village standards—would be about $577,182. Brandon said that split roughly into about $300,000 for Roscoe Center and the remainder for Hodges Run, and that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat