Fox Pointe plat 6 approved; trustees outline next steps, one-year public-improvement window
Summary
The board approved the final plat for Fox Pointe, plat 6. Staff said the developer must provide a letter of credit, the plat will be recorded with the county, and public improvements must be finished within one year of recording unless an extension is granted.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
The Village of Roscoe Board of Trustees on March 4 approved the final plat of Fox Pointe, plat 6, and staff described the next administrative steps and expected timeline for public improvements.
Brandi, a village staff member, told trustees that with the board’s approval the applicant will circulate a signed mylar final plat for signatures and establish a letter of credit to secure public improvements such as roadways, storm sewer and sidewalks. “From the date that it is recorded, the developer has one year from that date to complete all the public improvements unless they come back and ask for an extension of that,” Brandi said. She added that the developer is working on a funding agreement with Winnebago County to cover some intersection improvements not required specifically by the subdivision but sought by the county to avoid future pavement work.
Brandi said staff will request an estimated construction schedule from the developer. She estimated that public-improvement work could begin in late April or early May at the earliest, noting asphalt plants typically open in April; private home construction often follows completion of public improvements.
Trustees approved the final plat by recorded vote (see actions array). Staff said they will circulate the hard-copy plat, secure the letter of credit, sign the final plat as the last entity, and the applicant will record the plat at the Winnebago County recorder’s office. Once recorded, the one-year clock for public improvements begins.
Staff will report back with the developer’s anticipated construction timetable and the agreed letter-of-credit amount that will also reflect any county-requested roadway work.