Council approves preliminary plat for Magnolia Village, 25 patio homes on Barnett Boulevard
Summary
The Highland Village City Council approved a preliminary plat and tree plan for Magnolia Village, a proposed 25 single‑family patio‑home development at 102 Barnett Boulevard; the plan drew questions about protected trees and retaining walls during review.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Highland Village City Council on Sept. 9 approved a preliminary plat and tree plan for Magnolia Village, a proposed 25-lot patio-home subdivision on a roughly 4.364-acre tract at 102 Barnett Boulevard.
City planning staff said the application from DJB Development LLC had previously received a zoning change to a planned development district (single-family patio homes) on Sept. 24, 2024. The preliminary plat submitted for council review shows 25 single-family patio homes, sidewalks within the development, sidewalks along Barnett Boulevard, and required tree plantings: staff noted each lot would receive a minimum of two 4-inch-caliber magnolia trees. Staff and the city engineer reviewed the application for compliance with the cited ordinance and found it in compliance; the planning and zoning commission voted unanimously (5-0) to forward the plat to council.
During council questions, planning staff (Mr. Christen) explained the tree-protection rules in the city’s tree plan: a tree is designated protected unless it lies within a proposed easement, a retaining-wall footprint, a public right-of-way, or a proposed building footprint. Council members pressed the staff about several trees shown as protected on the plan but proposed for removal; staff replied that some of those trees would be affected by proposed retaining-wall excavation or required drainage grading and therefore could not be preserved in place.
The council voted to approve the preliminary plat and tree plan; the motion passed on a second and was recorded as approved by voice vote.
Why it matters: the approval allows the developer to move forward with detailed engineering and construction plans for a 25-unit patio-home subdivision under the previously approved planned-development zoning. The council’s questions about tree protection and retaining walls highlight tradeoffs between lot layout, grading/drainage requirements and tree preservation.
What’s next: staff will continue the platting process and permit review consistent with the approved preliminary plat and tree plan.