SUA approves contract amendment for West College sewer design, cites need for easement acquisition

5957710 · March 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved contract amendment number 2 for the West College Sewer Rehab project at the March 24 meeting. Staff said design is roughly 90% complete, about one-third of required easements are obtained, and construction funding is expected to include a $5,000,000 congressional directive from Senator Inhofe.

The Stowater Utilities Authority voted 5-0 March 24 to approve contract amendment number 2 (CA2) for the West College Sewer Rehabilitation project and to authorize related project expenditures and a budget amendment, according to the meeting record.

Chris Humes, the staff presenter, told trustees the project focuses on rehabilitating sewer lines and manholes in Westwood and the Greek housing areas and includes about 85 manholes around town. "The project is currently 90% complete, and then a third of the easements have been obtained," Humes said. He said the remaining work is to finish design, obtain the rest of the easements, then bid the construction work with construction expected to start the following year.

Humes described the project area as bounded roughly from King Street over to Jefferson and from University down to Sixth Street, with a small section off Eiler, an aerial crossing on Willis Street, and a crossing under Sixth Street at Country Club that will require replacement because video inspection showed a hole in the sewer pipe where it runs in a casing.

Humes said about 70% of the CA2 fee increase is from third-party easement acquisition work, including surveys and title work, and that project consultant fees and added scope have contributed to higher costs. He also said construction funding will include a $5,000,000 congressional directive from Senator Inhofe.

Staff recommended approving CA2 for a fee stated earlier in the meeting as $574,446, authorizing the general manager to execute CA2 and related documents, authorizing total project expenditures (figure in the transcript is not clearly stated), and approving a related budget amendment. Trustees moved, seconded and approved the staff recommendation by a 5-0 vote.

The transcript records the approval and the staff explanation; the record does not list individual trustee votes by name beyond the roll-call tally of 5-0, and some dollar figures recited by staff later in the item were garbled in the transcript and are noted below.