City outlines stage and restroom projects for Hazel Tilton Park; aims for Oct. 18 inaugural concert
Summary
The city manager said staff redesigned a planned stage to save about $200,000 and expects to begin erecting a pre-engineered stage foundation this week; a restroom structure modeled on the Love's Lookout rest stop and several pier improvements are also underway.
The Jacksonville City Manager told the council that crews will begin work on a stage foundation at Hazel Tilton Park later this week and that the city expects an inaugural concert on Oct. 18.
The manager said the original architect-designed stage bids exceeded budget and, after rebidding twice, staff redesigned the project using pre-engineered components and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat