The Brentwood Town Planning Board continued the site‑plan review for an application at 1 Smith Road to the board’s November meeting to give applicants time to complete stormwater work and related engineering submissions.
Planning staff said the engineer hired by the applicant told them additional work was required and could not be completed in time for the current meeting. Board members discussed options including ending the process and initiating code‑enforcement steps if the applicant fails to show forward progress. One board member said patience was "wearing thin" and the board will not grant another continuance on its own if the application shows no movement at the next meeting.
A motion was made to continue the matter to November 6; the board voted in favor. Board members instructed staff that if the applicant fails to submit the required materials by the continued date, the board may close the review and pursue enforcement actions.