Bullitt County construction updates: access‑road widening, drainage work and change orders presented
Summary
Facilities staff reported progress and site issues at Bullitt East and North Bullitt campuses, recommended several change orders (including widening an access road from 15 to 20 feet) and noted a roughly $130,000 credit on a baseball/softball project.
Kate Noble Ward, presenting construction updates to the Bullitt County Board of Education on Oct. 20, 2025, said work is underway on multiple school projects and described site‑specific issues and recommended change orders that are on the agenda for signature.
Ward reported that at Bullitt East the project is “underway with foundations” but there are water issues in a pump room that are being tracked by the board’s third‑party special inspector. At the physical science center for Bullitt East she said crews are adding storm‑water inlets “to take on some additional storm water” and recommended…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat