Fulshear EDC hears progress report on Harris Street project; contractor seeks extra days

5965364 · October 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff told the Fulshear Development Corporation that Phase 1 paving is nearly complete, sanitary sewer work is mostly done and the contractor is seeking additional days; staff and board members discussed change orders, progress estimates and potential liquidated damages.

Matthew Riley provided the Fulshear Development Corporation an update on the Harris Street infrastructure project at the board's Oct. 20 meeting, saying paving for Phase 1 is nearly finished and sidewalks and intersections have been poured. "Paving for phase 1 is almost complete," Riley said, and added the temporary pump station for the detention pond was installed and tested.

The update matters because the project is on the contract's critical path and the board raised concerns that the contractor's invoicing and claimed days on the job do not match the board's view of physical progress. Riley told the board he calculated about 40% actual progress after the pending Pay Application 8 is processed; staff said the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans