County administrator reports progress on sheriff's office construction, cites earlier natural-gas well delay
Summary
County Administrator reported construction progress on the sheriff's office, saying elevator shaft work is advancing, masons will move to juvenile court area and that hitting a natural-gas well on May 1 caused about a 19-day delay now reduced to about 10 days through sequencing and logistics.
Get email alerts on the Infrastructure Construction topic
No spam. Unsubscribe anytime.
The county administrator provided a construction update on the sheriff's office project, reporting that foundation and elevator-shaft work are progressing and that crews are moving toward work at the juvenile court site.
The administrator said, "As you can see, the 2 of the elevator shaft is, I think, by my interpretation, about to Level 3. So you have the Basement 12, and I think they're forming up 3 as we speak." He told the board that masonry crews will migrate toward the juvenile court and that crews are redoing the juvenile court parking lot so Judge Veil Leon, court employees and visitors will have secure parking connected to the sheriff's office.
The administrator explained that the project hit a natural-gas well on May 1 that "slow[ed] things down a bit. That was about a 19 day delay, but just through logistics and planning, I'll give Gilbane and and all the vendors a heck of a lot of credit thus far. They've got that down to 10 just through mobilization and sequencing, etcetera." No vote or decision was recorded; the report was informational.
The administrator said the parking work has "about a 3 to 4 week timeline left" and thanked court employees for using alternate parking arrangements while work continues.