Bethel Park SD: Elementary school construction on track; change orders, contingency and moving plan discussed

5844646 · September 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District and construction representatives reported major systems complete, academic wings targeted for July 2026 and a proposed post‑Labor Day 2026 opening for occupancy; facilities staff outlined several change orders, a remaining contingency under $500,000 and an estimated valve change order of roughly $23,000 (exact figure not specified).

Construction representatives from Massaro presented progress photos and a construction update on Bethel Park School District’s new K–5 elementary school, saying major mechanical and electrical systems are in place and that academic wings are on schedule for completion in mid‑2026.

The presentation included photos of completed mechanical rooms, data and electrical rooms, and near‑complete window installation. A Massaro construction representative noted, "The windows almost I think they're about 90 to 92 complete with windows fully framed," and reported work on roofing, air and water barriers, and the storm shelter. The representative also said the site had reached "415 days today, without a recordable."

District administration and project staff addressed community concern about delays after a board member asked district leaders to "assure the community" about the schedule and safety of the building. A district administrator said, "at this point, we are on track to open the academic wings in July 2026," and added that classrooms, offices, cafeterias and kitchens should be "100% functional on the first day of school." The district also discussed that a space such as the auditorium (referred to in the meeting as the LGI) could finish after initial occupancy without affecting classroom instruction.

Facilities staff reviewed change orders and site issues discovered during excavation and utility work. The project manager identified a change order for over‑excavation under slab on grade for $54,178. He described encountering multiple natural springs while installing sewer lines, and said the team added a transition (described verbally as roughly $7,000) and additional stone and piping to divert groundwater to existing outlet structures. The project manager said this mitigation was installed so that surface water would route to existing drainage and would require an extreme, unprecedented downpour to overwhelm the system.

Staff also described credits and other change items: a deduct for scanning of the storm shelter roof, a credit back for security cameras that the school board will take over, and additional cabling for clocks. A significant over‑excavation item described verbally for "Hall of Wall 5" was referenced in the meeting; the oral amount recorded in the transcript was unclear (transcript: "for $1.85") and is noted below as not fully specified in the record.

The board asked about contingency funds. Facilities staff said, "You're under 500,000 on the contingency. Last I looked, it was in a $400,000 range." On potential plumbing costs, staff described an added isolation valve (to allow portions of the building to be shut off without impacting the whole facility) that was originally estimated at about $21,000; staff said the current estimate had increased such that "maybe we'll say $23.24 now" (exact figure not specified in the transcript and reported here as approximate).

Board members and staff discussed logistics for move‑in and an opening date. Staff said moving and furniture installation would occur July–August 2026 and the district’s proposal is "to open school the day after Labor Day in 2026" to allow time for teacher move‑in and final setup. Staff also said routine punch‑list work may continue after occupancy and that some exterior landscaping or finish items could continue while instruction is underway, similar to current work at Independence Middle School (IMS).

No formal vote on the change orders was recorded in the transcript excerpt; facilities staff moved the relevant items to the consent agenda for formal action at the consent vote. Board and staff encouraged posting progress photos and a walkthrough video on the district website to address community questions.

Clarifying details from the meeting include the listed change orders and contingency range, the estimated valve cost, the target dates for academic wings and a proposed opening date, and the construction team’s stated safety record and planned punch‑list approach.