Commission approves $28,155 change order for Main Street streetscape Phase 6 after sinkhole repairs

5838084 · September 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Lafayette Redevelopment Commission approved a $28,155.55 change order for William Charles Construction on the Main Street Streetscape Phase 6 project, bringing the contract to $2,430,655.55.

The Lafayette Redevelopment Commission approved a change order on Sept. 25 that increases the William Charles Construction contract for Main Street Streetscape Phase 6 by $28,155.55, bringing the contract total to $2,430,655.55.

Redevelopment Director Dennis Carson summarized the change order (Change Order No. 1) as covering additional and unforeseen work discovered during construction, including window-well enclosures around the Bison Financial Building, a sinkhole repair, downspout installation and delays related to utility conflicts. Carson recommended approval of the change order and said the additional work was necessary to complete the scope safely and to current standards.

A commissioner moved approval and the motion was seconded; the commission approved the change order by voice vote. No roll-call vote was recorded at the meeting.

Why it matters: The change order is a minor (about 1.2%) increase to the original $2.4 million contract but reflects common construction‑phase risks (unforeseen utilities and localized ground failures) that can affect timing and budgets. The staff stated the item represents discovered costs that must be addressed to complete the downtown streetscape work.