Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
Developers and county discuss Mountain Green town‑center layout, transmission line routing and infrastructure funding
Summary
Developers, landowners and county commissioners met to pursue a joint development concept for Mountain Green's town center, discuss Rocky Mountain Power transmission-line plans and identify next steps on sewer, water and a potential federal grant application.
Get email alerts on the Land Use Development topic
No spam. Unsubscribe anytime.
Developers, landowners and Summit County commissioners met to discuss a joint concept plan for the Mountain Green town center and to coordinate infrastructure needs, including sewer, water, access and Rocky Mountain Power's proposed high‑voltage line. The meeting produced a plan to convene engineers and prepare a concept map for a future work session.
The participants said the discussion matters because existing town‑center (TC) zoning requires 35 percent commercial land and current parcel boundaries and development agreements prevent the parties from placing all commercial acreage in a single clustered center. Participants also raised aesthetic and right‑of‑way concerns about Rocky Mountain Power's proposal to upgrade wooden poles to taller high‑voltage structures through private parcels, and discussed options to bury the line if feasible.
Developers and county representatives spent the bulk of the meeting on three interrelated topics: how to consolidate commercial acreage and densities across adjacent parcels; how to secure and size infrastructure (sewer, water and road access) so multiple properties can develop and connect; and how to respond to Rocky Mountain Power's transmission upgrade through the area. Participants agreed to produce a joint concept plan and reconvene with county staff and counsel.
The parties noted constraints from existing approvals and code. TC zoning requires a 35 percent commercial component; one participant said their 35‑acre property currently shows approximately 12.42 acres of commercial. Attendees said the parcels in question include parcel holdings of roughly 35 acres, 40 acres and other tracts controlled by a third party, and that a previously circulated memorandum of understanding and a petition/referendum exist but are not recorded in a way that would bind successors.
Rocky Mountain Power's proposal emerged as a major concern. Participants described the current distribution poles as wooden lines and said the utility plans to install taller metal transmission poles (participants used measurements of roughly 130 to 138 feet) and a larger 60‑foot right‑of‑way in places where a 20‑foot easement exists today. Attendees said the upgrade would change the appearance of the corridor and could limit allowed uses where the line crosses parcels; burying the line was discussed as an alternative but was described as expensive, with participants quoting roughly $1.0 million to $1.6 million per mile for undergrounding in earlier utility estimates. The group agreed to ask Rocky Mountain Power for a realistic, site‑specific cost and to coordinate further with UDOT and the utility on overhead versus underground options.
On infrastructure, participants agreed that sewer and water capacity and access design will determine realistic unit counts. Developers said they are preparing will‑serve and capacity studies; county staff and developers agreed that a concept plan tied to agreed unit counts is needed before ordinance language can be drafted or amended. One next step agreed at the meeting was a technical session with engineers to prepare a concept plan: attendees scheduled a meeting with an engineer for Monday at 3 p.m. and requested the county provide guidance on ordinance amendments once the concept is available.
The group also discussed funding opportunities. Participants described a federal "innovative finance and asset concessions" grant program with larger program funds available and an actual grant stream that could yield up to $1 million for planning or capital work; speakers mentioned a broader pool of related federal funds of roughly $45 million and an October 1 application deadline for one competitive round. Attendees said they would collaborate with county staff on a public‑private application.
No formal votes or binding agreements were made at the session. The parties agreed to: (1) assemble the properties that would be part of a joint development agreement, (2) prepare a consolidated concept plan and (3) return to a county work session with that concept and suggested ordinance language. They also agreed to request a cost estimate from Rocky Mountain Power for undergrounding and to explore grant funding to underwrite study or construction costs.
Next steps identified by participants include meeting with engineers to draft a concept plan, circulating a checklist of substantive items the county needs for an ordinance amendment, and a follow‑up work session once a concept plan is ready. Participants said the county commission and the private parties remain interested in a joint development agreement or similar mechanism but will not delay discrete approvals where a party can move forward without being held hostage by a joint process.
Ending: Participants said they will continue weekly coordination, refine a concept plan with engineers, and return to the county for a work session when a consolidated plan is ready.

