Superintendent says new high school about 15% complete; funding schedule may delay opening until 2027
5834725 · September 24, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
Dr. Bennett updated the board that new high school construction is roughly 15% complete, rain has delayed progress and staggered funding means a 2027 opening is likely unless funds arrive sooner.
Superintendent Dr. Bennett told the board on Sept. 23 that construction of the district's new high school is approximately 15% complete and that the project timeline has been slowed by rain and the district's funding schedule.
Dr. Bennett said a site tour and updates from project staff indicated the project is "about 15% of the way completed" but rain has…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans