Public works recommends award for Schlegel Park 42‑inch storm main replacement; lowest bid reported at about $506,233
Summary
Public Works presented a recommendation to award the Schlegel Park stormwater main replacement contract to the lowest responsive bidder; engineers estimated $552,000 and the low bid was reported at approximately $506,233. Project funded by stormwater rates and a bond issued for the work.
Get email alerts on the Infrastructure Works topic
No spam. Unsubscribe anytime.
Public Works Director Maria Sarah told council the department plans to present a bid award for a 42‑inch stormwater main replacement in the Schlegel Park area at a future council meeting. The pipe lies within a Corps of Engineers easement and a condition analysis found root intrusion and failed prior linings that require replacement.
The project was publicly bid with six valid bids and one nonresponsive submission. Director Sarah said the lowest responsive bidder submitted about $506,233, which was below the city engineer’s estimate of roughly $552,000. She said the work is fully funded from stormwater rates and a bond issued to finance the construction; the repair also helps meet renewal conditions with the Corps of Engineers and avoids risks such as potential sinkholes.
Staff will return next week with the formal recommended award and required contract documents.