Board approves $5,230 change order to adjust private gate on 543 bridge replacement

5822028 · September 23, 2025

Summary

A $5,230 change order will replace a private fence and relocate a gate on the 543 bridge replacement project after designers omitted the relocation from final plans; the cost is covered by the project's grant.

Commissioners approved a change order on Sept. 23 adding $5,230 to the 543 bridge replacement project to relocate a gate and replace fencing on private property. County staff explained that the project’s design had assumed an existing gate location would be usable, but when the road height was raised to clear a culvert, the gate became inaccessible. The contractor will adjust the gate and fence to restore access to the Trujillo property. County staff said the cost is covered by the project grant. The board voted to approve the change order. No objections were recorded in the public transcript.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source