Haslet developer to rebuild Sweetgrass Phase 2 panels after city testing finds subgrade and compaction defects
Summary
Engineering staff told the council that Sweetgrass Phase 2 streets showed panel cracking and subgrade problems; the developer agreed to reconstruct affected panels under a city‑approved remediation plan and testing program, with work expected to continue into October.
City staff told the council on Sept. 17 that Sweetgrass Phase 2 (streets and utilities) showed signs of early concrete panel distress and subgrade issues; the developer has agreed to a reconstruction plan and testing program.
Staff described field observations of joint failures, edge cracking and sections with standing water. A series of tests and panel pulls notified the city that some fills and lifts were not compacted to…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat