City outlines State Route 619 corridor planning, sewer phase‑2 cost estimate and $3 million funding gap
Summary
City staff briefed council on State Route 619 corridor planning and sewer infrastructure needs, reporting a roughly $9.4 million estimate to convert an existing package wastewater plant to a pump station and a $3 million funding gap the city plans to pursue in upcoming capital and congressional funding rounds.
Get email alerts on the State Route 619 Infrastructure topic
No spam. Unsubscribe anytime.
City staff reported that OHM will present the State Route 619 corridor community planning grant findings and discussed sewer and water infrastructure needs tied to potential development along the corridor, including an estimated $9.4 million cost to complete Phase 2 of a sewer project and a roughly $3 million funding gap the city plans to pursue through capital budgets and congressional funding requests.
Why it matters: The corridor planning and sewer capacity influence whether and where new development can tie into municipal sewer and water systems; funding decisions and pump station capacity will shape near‑term development opportunities and infrastructure timing.
What staff told the council - Corridor planning: OHM will present ideas from the community planning grant about land‑use possibilities and funding sources for projects along State Route 619. The city won a competitive community planning grant and OHM’s work will inform potential capital projects. - Sewer capacity and Phase 2: Staff reported that phase 2 — converting the Zelle Wright package plant to a pump station so flows go to the regional wastewater treatment plant — has a planning cost estimate of approximately $9,400,000. The city currently has about $6,500,000 dedicated from prior capital budget and county commitments, leaving an estimated funding gap of roughly $3,000,000. - Funding efforts: The city has an outstanding request for congressional‑directed spending (earmarks) for part of the funding and staff said they intend to pursue the remaining gap in the 2026 capital budget cycle. Staff reported coordination with the county and with congressional offices on submitted requests. - Water planning and remediation coordination: The administration noted ongoing conversations about a water loop project that would extend water to support development and approach the BP remediation area; authorities and potential partners (including BP and state agencies) are being engaged as the city assesses feasibility.
Discussion versus action - Discussion only: council received briefings and staff updates; no final appropriation or contract award was made for the Phase 2 sewer project at this meeting. - Direction/assignment: staff said they will continue pursuing funding options and will return with refined project materials and funding requests.
Clarifying details from the meeting - Phase 2 cost estimate: approximately $9,400,000. - Funds currently committed: about $6,500,000 (capital budget and county contributions identified by staff). - Funding gap: roughly $3,000,000; city pursuing congressional and state capital funds. - Timeline: staff said they expect deeper design and procurement activity in the coming year if funding is secured; specific construction timing depends on funding and permitting.
Contact: staff asked council to stay engaged and said they will circulate materials related to OHM’s corridor presentation and to the funding requests when available.