Haslet Parkway work halted at Station 69; city refuses final acceptance citing incomplete utilities and right‑of‑way issues
Summary
City engineers told the Haslet council that the Haslet Parkway project stops at Station 69 and remains only substantially complete because utilities, grades and right‑of‑way conditions prevent the city from accepting and taking maintenance responsibility.
Haslet city staff told the council on Sept. 17 that the Haslet Parkway construction, as presented for final acceptance, is only “substantially complete” up to Station 69 and the city would not accept maintenance responsibility until a list of outstanding items is corrected.
City engineer Mike Anderson said a staff walkthrough and inspection late this spring found utility structures and roadway elements that the city could not safely maintain in their current condition. Anderson described submerged or partially completed manholes, utility…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat