LaSalle County awards Brookfield Township bridge contract to Gillen Construction

5788868 · September 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

LaSalle County highway staff recommended and the committee approved awarding the Brookfield Township bridge replacement contract to Gillen Construction for $389,920.10, the lowest responsive bid; the project will replace a small bridge with a precast triple-barrel culvert and is planned to be staged to limit traffic disruption.

LaSALLE COUNTY — The LaSalle County Highway Committee voted to award a bridge replacement contract in Brookfield Township to Gillen Construction for $389,920.10, the low responsive bid, county staff said during the committee meeting.

County highway staff told the committee four bids were received: Gillen Construction at $389,920.10; Illinois Valley Excavating at $438,476.25; Deconstruction (bid) at $393,782.20; and Toby’s Construction at about $580,429.00. "I recommend we award it to Gillen Construction for $389,920.10 as they are earning the engineer's estimate," a highway staff member said. The committee approved the award on a voice vote; the motion was made and carried during the letting report.

Nut graf: The project replaces a small bridge near the state park with a precast triple-barrel box culvert; the work will be staged and serves a dead-end road, county staff said. Staging is intended to limit closure time for the adjacent marina area and local traffic.

County staff described the site as a small bridge adjacent to a state park that carries a dead-end road. The engineer's estimate and the low bid were close enough for staff to recommend acceptance; the committee approved the recommendation and the motion carried.

The highway department said the award follows the formal letting process and that construction will be scheduled in coordination with other county projects. No timetable for construction start or completion was provided in the meeting discussion.