Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Rockport‑Fulton board hears construction update on new high school; substantial completion dated for Feb. 2026

5870961 · September 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Teal/Claycomb representatives told trustees the new Rockport‑Fulton High School is progressing, with mechanical, ceiling, and finish work underway and a substantial completion scheduled for February 2026. The board heard contract amounts, percent completion per billing and outstanding change orders tied to time extensions.

Contractors for Rockport‑Fulton ISD told the board on Sept. 16 that construction of the district’s new high school is advancing through interior finishes and site work, but the timeline for district occupancy has shifted and change orders remain under review.

Representatives from Teal/Claycomb and Steel Construction described recent progress during the board’s Bond 2022 project update. “We continued installation of the finishes such as the wall tile, drywall, paint, and we also continued installation of the low voltage wiring,” Teal Construction’s…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans