Board approves $251,701 change order for radio tower site after retaining‑wall and site modifications

5844454 · September 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Supervisors approved change order No. 2 for the county radio tower project totaling $251,701 to be paid from fund '94, citing unexpected site work including an extensive retaining wall and foundation changes on the chosen tower location.

Richland County supervisors approved a $251,701 change order Sept. 16 to the radio tower construction contract after engineers and contractors determined additional site work was necessary at the selected tower location.

County staff said the original preferred site fell through after negotiations with the landowner, forcing the project to pivot to a nearby location that presented more challenging ground conditions. Mike Day, the county’s project representative, told the board the site required an extensive block retaining wall because the ground sloped sharply away from the road. "The cost of what you're seeing here is born out of the ground being, falling off from the road and needing a retaining wall," Day said, adding the wall requires large block units trucked in on multiple semi‑loads and that the work includes footings and changes to the shelter foundation and fencing.

Day apologized for not having a complete line‑item breakdown for one portion of the work—in the executive and finance committee some supervisors had asked for a detailed backup for a $192,000 line. He told the board staff would provide the requested breakout of labor, materials and drainage costs.

The board approved the change order. No formal roll‑call detail beyond the voice vote was recorded in the public transcript for the final approval. Supervisors also heard that an increase to the contract raises associated bonding costs, which are passed through when contract amounts change.