Jackson County roads update: Prairie Creek bridge work, culvert replacement and staff recruitment discussed
Summary
County engineer staff updated the board on a Prairie Creek bridge/culvert project, a temporary closure expected during harvest, pile driving for bridge foundations, a 15-ton weight limit on the repaired structure, new equipment delivery and ongoing recruitment for an assistant engineer.
Get email alerts on the Public Works Roads topic
No spam. Unsubscribe anytime.
County public-works staff told the Jackson County Board of Supervisors on Sept. 16 that crews will inspect pile driving for a Prairie Creek conservation project this week and that a nearby bridge will be removed and replaced with a corrugated metal tube (66-inch culvert). Staff said the closure could last up to a month to allow removal of the old bridge and installation of the replacement structure, and that the repaired crossing will be posted with a 15-ton weight limit, not returned to an unrestricted bridge.
An engineer's-office staff member reported survey work after clearing trees and brush to determine final culvert orientation and ordering. Pile driving will begin on one of two bridges the contractor is building, and county crews will inspect the work on behalf of conservation officials. County staff said they had notified the public about road and bridge closures.
The board discussed timing of the closure during harvest and agreed to be expeditious while ensuring the work is done correctly. Staff explained that leaving the culvert replacement for a month was preferable to ordering material too early and risking incorrect fit on steep slopes.
The engineer's-office also reported equipment updates: a skid loader with a mulching head arrived for operator training; crews completed a reclamation process on roads that some residents praised, although staff warned that dry conditions can cause washboarding after grading until moisture re-compacts surfaces. The office said it will begin recruiting for an assistant engineer and that Tom from the engineer's office will attend next week's meeting in staff's place while recruiting continues.
No formal vote was required for the operational updates; the board accepted the department's information and asked staff to continue public notifications and to prioritize safety during harvest-season construction.