City engineer reports progress on Commerce Park well and East Wall street utility work; timeline remains through year‑end
Summary
City Engineer reported well development underway and plant site work progressing; storm sewer installation and utility conflicts with a fiber installer were noted, with electrical work estimated to take about two more months before TCEQ submittals for potable use.
City Engineer Miles Miloszwick briefed the Uintexa City Council on utility and street projects at the Sept. 15 meeting, describing progress and outstanding coordination tasks.
Lede: The Commerce Park well is downhole and plant site concrete slabs and equipment placement are underway; electricians are expected to need about two more months of installation work before well development and TCEQ sample submissions can move forward.
Nut graf: Miloszwick said the well is being developed and plant construction is advancing, but the city must coordinate remaining electrical work, programming, and utility location matters. He also reported storm‑sewer installation on East Wall Street and unresolved conflicts with a fiber‑installation contractor that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat