Central High parking expansion debated; board asks for design and cost follow-up
Summary
Board members and staff discussed options, engineering unknowns and community priorities for expanding Central High School parking; staff recommended more detailed engineering and construction cost estimates before any decision.
Get email alerts on the Facilities Parking topic
No spam. Unsubscribe anytime.
Board members spent an extended portion of Tuesday's meeting discussing possible expansion of the Central High School parking lot to address a shortage of student parking permits.
Board members and staff outlined two conceptual approaches: a smaller expansion using the current entrance (likely less costly and quicker) and a larger reconfigured entrance that would require road work and be substantially more expensive. "That scenario is very costly," a board member said of the larger option.
District facilities staff and community members discussed engineering uncertainties that affect cost: soil borings can be locally unrepresentative, stormwater permitting and required runoff mitigation can raise costs, and undercuts for unsuitable soil would increase expenses. A community member with construction experience estimated a lower-range cost in conversation with staff, while district engineering estimates were higher. Facilities staff said estimates ranged from approximately $550,000 to more than $1.2 million depending on options and stormwater requirements; construction-manager estimates cited in the meeting suggested a midpoint in the $565,000'$750,000 range depending on alternates and site constraints.
Board members emphasized they wanted better data before advancing design or bids. One board member asked the district's engineering consultant Ericsson to provide a schematic layout showing whether stormwater would be managed above- or below-ground, and for the district to obtain a construction manager's estimate to refine costs. Facilities staff estimated that a firm like SMC could produce a budget-level construction estimate for a few thousand dollars.
Why it matters: parents, student-athletes and staff raised parking availability as a recurring concern; juniors and seniors who participate in after-school activities are particularly affected when permits are limited. Board members said community input will determine whether to proceed.
Discussion versus decision: the session was exploratory. No funding or bid authorization was approved. The board asked for more detailed engineering drawings, a construction-manager cost estimate and additional community engagement before any formal project authorization.
Next steps: staff will ask Ericsson to produce an updated schematic and stormwater approach, request a budget estimate from the district's construction manager, and report back to the board. The board encouraged the communications team to solicit community input on priorities and trade-offs before staff prepares bid-ready documents.