Board approves $3.02M waste‑water pay application; sludge press delivery expected in October

5797478 · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved pay application No. 23 for the wastewater treatment plant improvements for $3,018,880.42 on the consent agenda. Staff later updated the board that a key sludge press piece of equipment is due to arrive and start-up work in November.

The village board approved the consent agenda, which included pay application No. 23 for the wastewater treatment plant improvements project in the amount of $3,018,880.42. The consent agenda was moved and carried by roll call.

During reports later in the meeting, project representatives and staff provided an update on the wastewater treatment plant improvements. Seth reported the sludge press — a major piece of equipment for the plant — was targeting delivery on Wednesday and that many pieces of equipment in the Sludge Press Building are scheduled for startup in November. Staff said supplier delays have been the primary challenge and that the contractor IHC and the engineers are pushing manufacturers to deliver equipment.

The updates characterized project progress as positive overall while noting ongoing equipment delivery delays. No change orders, funding reallocations or new contract approvals were recorded in the meeting transcript; the board recorded the pay application approval as part of the consent agenda.