Haslet staff say Verona Drive failed due to poor compaction; city to pay repairs after maintenance bond expired

5774654 · September 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council received an update that Verona Drive in The Vines subdivision is collapsing likely because soil was not compacted properly during construction; inspections found sewer lines intact and city staff said the maintenance bond has expired, so the city will cover repairs.

City staff informed the council Sept. 15 that sections of Verona Drive in The Vines subdivision are failing. Public works and engineering staff inspected the site and concluded the most likely cause is inadequate soil compaction prior to the road build. The city performed scope inspections on the sewer line under the failing road and reported the sewer was not compromised.

City Engineer Michael Anderson told the council that because the developer's maintenance bond period (two years) expired before the deterioration was discovered, the city is responsible for repairs and will schedule corrective work. Staff said the affected segment is approximately 380 feet running north from Syracuse Street. Council members were told the city would perform the necessary repairs; staff will report details at a forthcoming workshop on street failures.

The council received the update as part of routine administrative project reporting and did not take a separate formal vote on the repair method at the Sept. 15 meeting.