Consultants told the facilities committee that construction at New Windsor Elementary would begin immediately after the meeting, with site mobilization focused on a temporary bus loop and stormwater fixes intended to reduce impacts on neighboring properties.
Tom Ritzenthaler of CS Arch said the project uses phased construction because the school will remain occupied. The team plans to cordon off areas with temporary walls; work in areas B, C, D and E will include second-shift mechanical upgrades and summer first-shift activity. Ritzenthaler said a building swing schedule is planned for Jan. 31, 2027, with substantial completion in May 2027 and final closeout in August 2027.
The presentation described a design change that removed a remaining portion of an old building so the new plan would avoid a courtyard scheme and be more economical to build. District staff said they had met the contractor and a subcontractor to review construction wall details for student protection and that the temporary bus loop work was scheduled to start the following Saturday.
Presenters emphasized site staging work, the sequencing of parking-lot renovations and the goal of limiting construction impacts. No public comment or formal approvals were recorded for this item at the committee meeting.