Council signs certificate and approves final invoices after CCMG paving finishes, project 1.2% over bid
Summary
Town staff reported the CCMG paving contract is complete; the council signed the certificate of substantial completion and approved final payments after staff explained a $7,671.02 overrun (1.2%) caused by extra sidewalk repairs and milling damage.
The Town Council signed the certificate of substantial completion and approved final invoices for the town’s 2024 CCMG paving project after staff reported the contractor finished paving and addressed punch-list items.
Staff said the original bid was $642,887.15 and the final contract amount was $650,558.17, an overrun of $7,671.02 (about 1.2 percent). The reported reasons were additional sidewalk spot replacements and “scabs” — areas where the milling machine pulled up chunks of existing pavement…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat