Palmdale Aerospace Academy delays full student-meal rollout until Jan. 1 after kitchen equipment and electrical work
Summary
Chief Business Official Ms. Azura told the board that planned October rollout of expanded food service for middle and high school students is delayed to Jan. 1 because of equipment and electrical/gas work; limited items may be offered in October.
Get email alerts on the School Food Services topic
No spam. Unsubscribe anytime.
Chief Business Official Missus Azura told the Palmdale Aerospace Academy Board of Directors that the planned October rollout of expanded food service for middle and high school students will be delayed until Jan. 1 so contractors and staff can complete electrical and gas work and install walk-in refrigeration and a convection oven.
The delay means the full kitchen will be completed when students are not on campus. "So we are looking at the length of full rollout until January 1 after winter break, and that will give, all the parties time to get the kitchen up and running everything installed when children are not here," Azura said. She added the food-services team will try to introduce some items in October so the program can show incremental progress.
Why it matters: the schedule change affects when middle- and high-school students will receive meals prepared on campus rather than alternative arrangements. Azura said facilities crews must redo some electrical and gas lines before new equipment can be used. The board did not take formal action at the meeting; this was a staff report.
Details from the meeting: Azura said facilities and food-services staff are coordinating installation and that the director of food services and assistant director will work on partial rollouts in October. The presentation noted equipment delays as the reason for postponing the full program. No estimated additional cost or contractor names were provided during the report.
What comes next: staff will continue equipment and utility work and report progress to the board; no timeline update beyond the Jan. 1 target was offered at the meeting.