Murray bond projects move to masonry and tilt‑up work; crane expected in late September
Summary
Construction for the Murray High addition and junior high is progressing through footings and masonry; tilt-up panels for auditorium and gym are being cast and a large crane is scheduled for the week of the 22nd to set panels.
Get email alerts on the Capital Projects Construction topic
No spam. Unsubscribe anytime.
District Director Taggart told the board that construction on bond-funded additions at Murray High School and the junior high is progressing on schedule, with footings and foundations in place at the high school and early masonry and steel-column work starting. At the junior high, Taggart said some slab-on-grade work is complete while other areas remain under foundation work; crews are casting tilt‑up panels for the auditorium and the gymnasium and expected to set panels when a crane arrives. He said casting beds for gym panels were poured the morning of the meeting and that the crane delivery — described as multiple semis to assemble the crane — is tentatively scheduled for the week of the 22nd (week number provided by contractor but not a specific calendar date). Taggart said the projects are tracking on schedule and added that masonry crews were making visible progress; staff said the district would notify the board when an exact crane date was available.