Planning board approves Irving Farm solar site design review
Summary
The Caribou Planning Board approved a final site design review for a solar array proposed at the Irving Farm property, finding it generally consistent with the city’s comprehensive plan and applicable site criteria.
Get email alerts on the Solar Project topic
No spam. Unsubscribe anytime.
At its meeting called to order at about 6:03 p.m., the Caribou Planning Board voted unanimously to approve the final site design review for a solar array at the Irving Farm property. The board closed the public hearing and approved the plan as presented, with four members voting yes.
Board members said the solar array would serve Irving Farm’s on-site power needs and noted the site is associated with a storage and packing facility on the property. Board members assessed the project against the planning board’s site-design criteria and concluded the proposal is generally consistent with the comprehensive plan’s support for local agricultural businesses.
Board discussion went through standard review criteria: traffic (deemed not applicable for new traffic impacts), site access (two access roads identified), parking and pedestrian circulation (not applicable), open space (surrounded by open space), emergency vehicle access (available from the main road), erosion control and stormwater (panels are to be placed in grass; erosion control measures judged adequate), existing landscaping and infrastructure (adjacent to power lines), and exterior signage (limited to safety/warning signage shown in plans). Board members noted the panels are arranged in rows and that the plan identifies two inverters serving different arrays within the field.
Planning staff and board members also discussed details visible in the packet. One member asked whether panels were fixed or tracking units; staff and members noted the design shows fixed panels and that tracking systems are typically more expensive and can create additional maintenance concerns. The board reviewed a plan legend that differentiates arrays by inverter zone and confirmed with staff that the differing colors on the plan represent different inverter groupings rather than panel types.
No substantive public testimony was offered at the hearing. After closing the hearing, a board member moved to accept the plan as presented and another member seconded. A roll-call vote recorded four yes votes and the motion passed. The board directed staff to circulate the approved plan for signatures.
The approval is limited to the site design review as presented; no construction permit or building permit issuance was recorded in the meeting minutes. Construction and any required utility interconnection approvals remain subject to normal permitting steps and utility review.
Board members present for the vote included Steve Wentworth, David (last name not specified in the transcript), and Eric (last name not specified), and one chair who presided; Penny (planning staff) assisted in packet and plan explanation. The plan packet referenced inverter labels and a site area of approximately 29 acres in the parcel description.