Summary

The committee approved forwarding a request to allocate $102,000 in parks levy funds to cover additional contractor compensation and temporary locker room costs after manufacturing and supply delays extended the Federal Way Community Center locker room project.

The committee voted to forward to the Sept. 16 consent agenda a staff request to allocate $102,000 from the parks levy to cover additional costs tied to delayed delivery and installation of locker room lockers and partitions at the Federal Way Community Center.

Parks contract administrator Autumn Gressett and project staff told the committee that manufacturing delays — including hurricane impacts to supplier delivery schedules — required the contractor to extend temporary locker‑room arrangements and that Merit Construction requested additional compensation linked to the schedule extension. Staff said roughly half of the requested allocation would cover additional contractor compensation and half would pay for extended temporary locker‑room facilities so pools could remain open while final work finishes.

Staff said substantial completion was anticipated “around the 26th of this month” (presentation phrasing) but that an opening date would depend on punch‑list work and final inspections. Committee members asked for a concise accounting of the total cost of work at the community center (slide replacement, pool repairs, temporary locker rooms and the locker‑room contract) and staff agreed to provide a single, concise spreadsheet for council members ahead of the next council meeting.

The committee approved forwarding the allocation to the Sept. 16 consent agenda; staff said they will continue to manage close‑out activities and report timelines and a final cost summary to council.