Select Board endorses moving forward on Harbor Master building; $1.5M shortfall identified
Summary
After a decade of planning and multiple bids that exceeded estimates, the Select Board agreed Sept. 10 to proceed with final construction documents and to seek funding options for a projected $1.5 million shortfall to replace the downtown Harbor Master building and public restroom facility.
Get email alerts on the Harbor Infrastructure topic
No spam. Unsubscribe anytime.
The Select Board on Sept. 10 endorsed proceeding with final construction documents and a bid schedule for a replacement Harbor Master building and public restroom facility at the town pier, while acknowledging a projected funding gap of roughly $1.5 million. Project background: Charles Gibson, project manager for the Harbor Master site, summarized a multiyear process that included a needs analysis, structural studies and several rounds of bidding. Initial professional estimates in 2021 were approximately $2.5 million, but bids after the COVID era returned much higher prices. A May 2021 bid round produced a low bid of about $4.8 million against earlier estimates; a 2023 re‑bid returned a low bid near $8.9 million. Value engineering and permitting steps reduced cost drivers: the team secured waivers to avoid an elevator and replaced wrap‑around handicap ramps with a chairlift to limit foundation and ramp costs; ceiling heights were adjusted to reduce building volume while maintaining functionality. Recent professional estimating (RGB) produced a current estimate near $6.1 million. Town funds on account total just under $5.0 million, leaving a projected gap of about $1.5 million to reach a July 2026 construction target. Select Board discussion and funding: Board members expressed support for moving forward but discussed funding options. Several suggested the town consider offshore‑wind settlement funds (the Vineyard Wind blade failure settlement) as an appropriate waterfront‑dependent use; others said free cash or borrowing and a future town‑meeting appropriation are possibilities. The board instructed staff to continue finalizing construction documents, advance a bid schedule and return with funding recommendations. Why it matters: The building serves critical public functions—restrooms and showers for harbor users—and houses Harbor Master operations that supervise a busy municipal pier. Town officials said the existing building is structurally deficient and not code‑compliant, with failing restroom floors. Next steps: Staff will finalize bid‑ready construction documents, continue permitting and return with specific funding options and a timeline for a public appropriation or other funding mechanisms.