Falling Branch Corporate Park Phase 2: 20-acre pad graded; water line and pump-station design cleared by Christiansburg and DEQ
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
Montgomery County staff reported that Falling Branch Corporate Park Phase 2 Site 2 now has a 20-acre graded pad, installed utilities and approvals for the pump station, with paving cited as the main outstanding cost.
Montgomery County staff reported construction progress at Falling Branch Corporate Park Phase 2, Site 2, saying a 20-acre graded pad is complete and work on paving is underway.
According to staff, Lot 7 has been sold and construction is active there; Lot 3 (the 20-acre pad) is complete with grading, topsoil, seeding and a 10-inch gravel base. The water line is finished and the Town of Christiansburg and the Virginia Department of Environmental Quality approved the pump-station design. Street lights have been installed.
Paving remains a major outstanding expense. Staff said paving is the next substantial item, with an estimated cost noted in the discussion at about $300,000. Installation of a natural gas line is in progress and has taken longer than staff expected. A change order reduced one contractor’s scope by about $31,000 and moved that work into a separate contract.
County staff said Christiansburg has requested funding to pave Parkway Drive all the way to North Franklin; that extension is listed in the Virginia Department of Transportation’s six-year plan but has not yet received VDOT funding. Staff described a process of reviewing smaller punch-list items once paving and substantial completion are reached; staff also noted that substantial completion triggers a 30-day window related to liquidated-damage penalties.
On market interest, staff said there have been inquiries—particularly from distribution uses along I-81 and other larger-site users—but high construction costs are limiting new speculative building. Staff pointed to bigger regional announcements, including Google data-center projects in neighboring Botetourt County, as part of the broader demand context.
Staff noted a modest topsoil deficit was addressed by moving material on-site. The county did not record any formal vote on the site update in the provided transcript excerpt.
