Council approves guaranteed maximum price for Palm Coast maintenance operations fuel depot; members press for clearer contract details
Summary
Council approved an approximately $8.0 million guaranteed maximum price (GMP) for the Maintenance Operations Center fuel depot (Phase 1B) and a construction contingency; several council members asked for clearer contract presentation and a copy of the original master contract before final implementation.
PALM COAST, Fla. — The City of Palm Coast City Council on Oct. 21 approved a guaranteed maximum price (GMP) contract amendment for the Maintenance Operations Center (MOC) fuel depot, with a construction contingency. The vote was unanimous.
City staff described the project as part of a larger MOC master plan that consolidates public‑works, utilities and stormwater functions on a single campus. Phase 1B covers construction of a municipal fuel depot with associated paving, landscaping, irrigation, fencing and utility work; staff said the Phase 1B GMP with Old Bayne Building Company is $7,984,870 with a construction contingency of $227,331.
Architect Eric Givo and staff briefed council on project status. The site‑development…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat