Fairport board hears construction progress, contractor-screening overview for 2023 capital project
Summary
District and contractors updated the board on 2023 capital project progress — library, STEM addition, tennis courts and track — and described contractor screening and on-site safety procedures.
The Fairport Central School District received an update on the 2023 capital improvement project and on contractor screening procedures at its board workshop.
District construction staff reported the overall referendum budget for the project as $45,000,008.27 and said the work currently concentrates on the library renovation and the STEM addition. The presentation said construction contingency originally totaled roughly $2,400,000 and that approximately $1,800,000 remains available after approved change orders and pending issues; construction contract allowances were stated as about $540,000.
Presenters said work in the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat