Selectmen approve $43,275 contract to reinforce footings for highway department cold-storage building

5967937 · October 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved a low-bid contract with Hussey Brothers to reinforce existing footings for a new cold-storage steel building at the highway department; the committee discussed broader project costs and the possibility of a mezzanine addition.

The Board of Selectmen on Oct. 21 authorized a contract with Hussey Brothers for footing reinforcement work related to the new cold-storage building at the highway department, approving a base bid of $39,375 plus a $3,900 contingency for a total of $43,275.

Public works staff said the work involves excavating around existing footings, reinforcing them and adding purlins where needed so the new steel columns will have adequate support. A structural engineer prepared the design the contractor will follow.

Budget context: the presenter said the purchase of the steel building itself and earlier work put the project in a neighborhood of roughly $140,000 for the building plus approximately $18,000 for demolition already contracted. The footing contract is the third contract tied to the project; additional costs remain possible depending on decisions about a freestanding mezzanine and other site work.

Board members asked for a consolidated cost summary; staff agreed to email a summary of total costs and expected outstanding items so the board could track the overall budget-to-completion number.

The motion to award the Hussey Brothers contract for $39,375 plus contingency passed unanimously.