Brookside subdivision: board sets occupancy threshold, timelines and approves 60-day extension
Summary
The Wells Planning Board adjusted final-occupancy rules for the Brookside subdivision, applying the board’s standard 10% holdback (rounded to three units) and setting a revised occupancy trigger. The board also granted a 60-day extension for the applicant to return with final documents and clarifications.
Get email alerts on the Brookside Subdivision topic
No spam. Unsubscribe anytime.
The Wells Planning Board on Monday reviewed a Brookside subdivision update, set a final-occupancy threshold consistent with past practice and granted the applicant an extension to finalize deed and plan details.
Developer Jason Lamont and consultant Craig Burgess described revisions submitted after staff review. Planning staff reported a revised deed had been received but needed review, and the fire chief asked for scheduling constraints for cistern testing so tests are not run in winter months when equipment can freeze.
Board decisions and direction - The board adopted its customary "last 10%" holdback on occupancies for this project and clarified that with 25 units total, the holdback equates to three final occupancies; the board set the milestone at 22 completed occupancies prior to the final pavement/occupancy releases. - The board voted unanimously to grant the applicant a 60-day extension to continue the workshop so staff and the applicant can reconcile plan notes, deed language and outstanding attorney comments. - The board discussed deed language limiting accessory dwelling units (ADUs) and short-term rentals and asked the applicant to include no-short-term-rental and no-ADU language comparable to other recent approvals if the developer agrees.
Why it matters: The board’s adoption of its standard holdback rule and the 60-day extension are intended to ensure the developer completes required infrastructure items — including ADA parking, pavement and deed restrictions — before final occupancy certificates are released.
Next steps: Applicant to provide revised deed language, confirm cistern testing windows per fire department request, and submit any remaining plan revisions for staff review during the extension period.