Louisa County officials say middle school project is about 92% complete and remain under budget
Summary
District staff reported the middle school renovation is 91.96% complete, with $20,265,741.30 spent (77.9% of budget) and a $12,000 contingency balance; CTE building footings and first-block work are underway and the district said the project remains on schedule.
Louisa County Public Schools staff told the school board the district’s middle school renovation is roughly 91.96% complete and the project is on time and under budget.
A staff member who presented construction photos and figures said the district has spent $20,265,741.30, which represents 77.9% of the project budget, and that the contingency balance for the school additions is down to $12,000. “We are on time and under budget for that project,” the staff member said.
The presenter showed images of the Second Floor, saying flooring, paint and ceiling work are largely finished and that the auxiliary gym and cafeteria areas are…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat