Southwest ISD receives construction updates on central office, Bob Hope and Alvarado projects
Summary
District staff and contractors told the board that central office, Bob Hope Elementary and Alvarado Elementary projects are progressing on schedule, with interior work advancing and several summer turnovers planned.
Get email alerts on the Construction Updates topic
No spam. Unsubscribe anytime.
District staff and outside contractors delivered updates on the Southwest ISD construction portfolio, reporting steady progress on the new central office, Bob Hope Elementary renovation and the Alvarado Elementary job site.
Presenters shared aerial photos and drone footage showing masonry and window installation, interior drywall and HVAC ductwork placement at the central office site; staff said the project is over halfway through payout and remains on schedule for fall completion. For Bob Hope Elementary, staff reported the interior renovation and a new classroom addition are near completion with the administration area and life‑skills spaces expected to be occupied by the end of the month and overall construction reported at about 65% complete.
At Alvarado Elementary the project team showed drone video and photographs from the day of the meeting, reporting that site utilities, foundation piers and the mud slab have been poured and that concrete slab pours were taking place that day. The Alvarado presenter said the project is approximately 12% complete and described where the gym, cafeteria, music/art and two‑story classroom blocks will sit on the site plan.
Across the presentations contractors described interior sequencing: once exterior enclosures are in place, trade work can accelerate on mechanical, electrical and interior finishes. Board members praised the pace and asked a few questions about schedule and warranty terms; staff replied that the McNair reroof warranty will be 20 years for the proposed overlay system and that some window and glazing work remains for the Bob Hope addition.
Staff noted communications materials — photos and meeting handouts — will be posted for trustees and the public. No formal board action was required on the information items; updates were provided so trustees could review progress and upcoming summer turnovers.