Mineola superintendent reports middle‑school gym HVAC work done; field and gas‑line reroute delay turf work
Summary
Superintendent Michael Naglas told the Board of Education on Aug. 28 that HVAC work in the nearly 100‑year‑old middle‑school gym is complete and that glass is being installed, but field work is paused pending National Grid rerouting a gas line and trades staffing issues have slowed follow‑up tasks.
Superintendent Michael Naglas told the Mineola Union Free School District Board of Education at its Aug. 28, 2025, meeting that the district has completed major HVAC work in the middle‑school gym and expects students to begin using the space as staff finish transitions.
"The current middle school gym, the one that we've had for 100 years, almost 100 years, is back in action," Naglas said. He described a compressed work window and late nights by contractors, noting that…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat