County staff reports slight delay in campus bridge project; concrete and paving dates set

5844485 · June 5, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff reported a minor schedule shift on the campus bridge project with grading, concrete, paving, landscaping and a final walkthrough scheduled between June 6 and the week of July 7; staff said the project remains essentially within budget.

County project staff updated the Campus Reconfiguration Committee on the status and near-term schedule for the campus bridge project.

Josh, who provided the update, said work has experienced a “slight delay” in mobilization but described a sequence of upcoming activities: subcontractor Colin McGuire is expected to complete grading by June 9; a concrete subcontractor will mobilize the week of June 16 to finish concrete work (curb, gutter, sidewalks and concrete pavement); asphalt paving is scheduled for June 23; site touch-ups and additional concrete work would follow; landscaping crews will complete planting and finish work afterward; and a final walk-through is planned between June 30 and the week of July 7.

A committee member asked whether the project remains within budget; the response reported it was “still basically in budget.” No formal action was taken; the update was informational and the committee approved minutes and moved on to other agenda items.