Council awards Shaker Boulevard pedestrian trail contract; successful bid $100,000 under estimate

5844373 · July 23, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved a contract award for the Shaker Boulevard pedestrian trail after bids came in below estimate; the successful bidder will start approximately five days after notice to proceed with a 75-calendar-day contract.

Council approved the low (successful) bidder for the Shaker Boulevard pedestrian trail at its July 22 meeting, awarding the contract to a cement contractor after a competitive bid process that came in about $100,000 under staff’s estimate.

Public works staff described a “good group of bidders,” said the successful bid matched the project estimate closely and noted a roughly $100,000 gap under the original estimate. Staff said competitive pricing reflected contractors’ desire to keep crews working as the season wraps.

Council asked questions about optional line items for crosswalk markings, concrete material uniformity across contractors and schedule. Staff said the alternate items covered thicker, longer‑lasting pavement markings and that all contractors would use the same concrete specification so repairs would match.

The contract includes a 75‑calendar‑day completion schedule; staff estimated work would start about five days after notice to proceed and finish sometime in October, weather permitting. Council approved the award by roll call.