Redevelopment Commission approves $153,444 change order for Hopewell West; completion pushed to Nov. 15
Summary
The Redevelopment Commission approved a $153,444 change order for the Hopewell West project to implement a soil management plan; the final contract amount was revised to $1,840,763.55 and the completion date moved to Nov. 15, 2025.
The Redevelopment Commission on Sept. 2 approved change order No. 1 for the Hopewell West project to address a soil management plan and extended the project completion date to Nov. 15, 2025. The approved change order adds $153,444 to the contract, raising the total to $1,840,763.55.
The change order was described at the meeting by Roy Eaton, city engineer. Eaton said the work stems from a soil-management plan that had not…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat