City staff said the FAA offered construction and design grants to rehabilitate pavement on the north side of the airfield between the self-serve fuel area and hangars; FAA will cover about 91% of cost, ADOT about 4.5% and the city roughly 4.5% (about $20,000 combined city share), with work expected to begin this fall.
Get email alerts on the Airport Grants Pavement Rehab topic
No spam. Unsubscribe anytime.
Sierra Vista — City staff presented two grant offers from the Federal Aviation Administration and a likely state grant from ADOT to fund pavement reconstruction and rehabilitation on the north side of the airfield.
A staff presenter told the council that "the Federal Aviation Administration has determined the project is eligible for federal funding and has extended grant offers to the city which will cover about 91% of the project cost for both." Staff said ADOT is expected to contribute about 4.5% and that the city's share for both grants combined would be "a little less than $20,000." If accepted, work is expected to begin later this fall.
Why it matters: the north-side pavement serves general aviation parking areas and taxi lanes adjacent to hangars; consultants and staff said the existing pavement is showing distress such as raveling, which can release aggregate and damage aircraft propellers and airframes.
Contracting and standards: staff said the work must be contracted and meet federal standards because it is federally funded. Council members also asked about airport maintenance equipment; staff said the airport has received a new sweeper sized to operate between hangars and that it is now in operation.
Discussion vs. decision: staff presented the grants and recommended acceptance; the meeting transcript records council discussion and positive comments from pilots and council members but does not record a formal vote in the provided transcript.
End note: staff linked the grants to the master planning work presented earlier, saying that the city's recent master-plan process supported eligibility for the federal cost-share on these projects.