Board approves $505,171.09 payment to Globe Contractors for Progress Drive sanitary relay work

5834925 · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved the contractor’s application for payment No. 1 to Globe Contractors Inc. for the Progress Drive Sanitary Relay Project, authorizing $505,171.09 while retaining a contract retainer for completion of remaining paving and landscaping work.

The Village Board approved contractor application for payment No. 1 to Globe Contractors Inc. for the Progress Drive Sanitary Relay Project in the amount of $505,171.09. Staff said Globe installed new pipe, backfilled and compacted to specifications and is completing remaining concrete, curb and paving work.

Staff explained that the contractor’s invoice showed $525,010 in gross progress but the village retained $20,838.91 per the contract as a holdback until final completion; the net payment requested was $505,171.09. "We always keep a retainer ... until that retainer will be for landscaping materials, make sure everything is done to satisfaction," a staff member said.

The motion to approve payment No. 1 was moved and seconded and carried on the board’s voice vote; staff said remaining paving will be billed in a later application and the retained amount will be released after final acceptance and any required landscaping.