Public services staff updated the council on the ASR‑86 verification project and related local street work. Staff said turn lanes north of Arione are complete and that work on the south side will continue for roughly two weeks, requiring a temporary closure of Sixth Street between Pearl Avenue and SR‑86 to complete medians, landscaping, waterline and electrical service work.
Staff advised that striping had not yet been applied and said advance social‑media notification explaining how new turn lanes and medians will operate would be beneficial. A council member noted driver confusion at the new lane configurations and encouraged a short instructional video or public notice.
Public services staff also reported progress on a Title 22 recycled water report that could enable future water sales to developers, and discussed an early‑stage concept to connect Fifteenth Street to improve traffic flow and reduce local residential cut‑through. Staff said the Redondo Sky Ranch Park expansion is nearing completion and other paving and thermoplastic striping projects are under way.
No council action was required; staff said they will proceed with construction notifications, striping and outreach.