Courthouse annex move nearly complete; county prepares for annex openings
Get AI-powered insights, summaries, and transcripts
SubscribeSummary
Commissioner report says furniture installation is finishing at the Albert Park annex, crushed-concrete alley improvements are complete and the facility will open for business Sept. 2, except for the tax office, which remains to be placed.
Commissioners received an update on courthouse renovations and county courthouse annexes at the Aug. 26 meeting. Commissioner Regent reported that furniture installation was in progress at the Albert Park annex and that crews had improved the back alley with crushed concrete to create a functional driveway.
The commissioner said the only remaining construction item was a tile backsplash in the kitchen and that doors would open for business on Sept. 2 except for the tax office, which still requires coordination. Staff showed a video of the key handoff and described final preparations.
The court heard general approval of the finished work and had no additional questions. A later agenda item that would have required closed-session discussion was tabled because related legal information from outside counsel had not arrived in time for the meeting.
