Board approves ETR Richardson Middle School flooring change orders; net reduction of $1,512

5830369 · September 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved multiple change orders for the ETR Richardson Middle School flooring and renovation project, with a net contract reduction of $1,512; a board member asked staff to clarify the missing change order #7.

The Springfield School District Board approved change order requests 1–6 and 8 from Donald Breisinger Inc. for the ETR Richardson Middle School flooring and renovation project on Sept. 25. The motion passed by voice vote, 7‑0.

The recommendation described a net negative adjustment of $1,512 for ceiling and wall enhancement work and additional flooring and vinyl cove base installation. President Lord presented the item; Dr. Joseph Hepp, board member, asked about change order request number 7 and whether it had been omitted or carried no change.

Staff did not have the answer at the meeting; Dr. Hepp asked staff to look up the status of request number 7 and report back. No amendment to the approved change orders was made at the meeting.

The board adopted the listed change orders as presented; staff committed to follow up on the status of change order request number 7.